Underground Utilities
January 2009 - August 2009
Eastside Interceptor Phase 4A - Part 3
El Paso, Texas
Owner El Paso Water Utilities
Value $3,321,232.00
Engineer Brown & Caldwell
- 2,057 LF of 48" Fiberglass Gravity Sewer
- 4,943 LF of 42" Fiberglass Gravity Sewer
- 90 LF of 24" Fiberglass Gravity Sewer
- 200 LF of 60" Steel Casing with an Akkerman TBM
- Depths of 30 to 40 feet
- Required two meter stations. The project was in existing soils open for future roadways by others.
- Required one bag crack dry non-flowable cement for embedment.
- Installed nine 60" sanitary sewer manholes
- Work performed in very sandy and usually windy conditions.